1. Who creates a product backlog for project initiation under Scrum cycle
A. Scrum team
B. Scrum Master
C. Product owner
D. None of these

2. Which accounting concept refers to the value today of future cash flow?
A. Present value (PV)
B. Net present value (NPV)
C. Opportunity cost
D. Sunk cost

3. Project charter is the responsibility of?
A. The project manager
B. The project sponsor
C. The project team
D. None of these

4. Which requirement gathering technique, focuses on suggestions by domain experts?
A. Alternative generation
B. Affinity Diagram
C. NGT
D. Expert Judgement

5. Which WBS design principle focuses on capturing all deliverables - whether internal, external or interim?
A. 100% rule
B. Mutually Exclusive
C. Level of Detail
D. Plan outcomes


Answers:        1 (C), 2 (A), 3 (B), 4 (D), 5 (A)


More Practice Test:.

https://www.vskills.in/practice/quiz/Project-Management

 

Apply for Certification

https://www.vskills.in/certification/project-management/Certified-Master-in-Project-Management



 For Support