Building A Test Plan- A test plan describes a series of steps JMeter will execute when run. A complete test plan will consist of one or more Thread Groups, logic controllers, sample generating controllers, listeners, timers, assertions, and configuration elements. 

Adding and Removing Elements

Adding elements to a test plan can be done by right-clicking on an element in the tree, and choosing a new element from the “add” list. Alternatively, elements can be loaded from a file and added by choosing the “merge” or “open” option.

To remove an element, make sure the element is selected, right-click on the element, and choose the “remove” option

Loading and Saving Elements

To load an element from a file, right-click on the existing tree elements to which you want to add the loaded element, and select the “merge” option. Choose the file where your elements are saved. JMeter will merge the elements into the tree.

To save tree elements, right-click on an element and choose the “Save Selection As …” option. JMeter will save the element selected, plus all child elements beneath it. In this way, you can save test tree fragments and individual elements for later use.

The workbench is not automatically saved with the test plan, but it can be saved separately as above. 

Configuring Tree Elements

Building A Test Plan- Any element in the test tree will present controls in JMeter’s right-hand frame. These controls allow you to configure the behavior of that particular test element. What can be configured for an element depends on what type of element it is.

The Test Tree itself can be manipulated by dragging and dropping components around the test tree.

Saving the Test Plan

Although it is not required, we recommend that you save the Test Plan to a file before running it. To save the Test Plan, select “Save” or “Save Test Plan As …” from the File menu (with the latest release, it is no longer necessary to select the Test Plan element first).

JMeter allows you to save the entire Test Plan tree or only a portion of it. To save only the elements located in a particular “branch” of the Test Plan tree, select the Test Plan element in the tree from which to start the “branch”, and then click your right mouse button to access the “Save Selection As …” menu item. Alternatively, select the appropriate Test Plan element and then select “Save Selection As …” from the Edit menu. 

Running a Test Plan

To run your test plan, choose “Start” (Control + r) from the “Run” menu item. When JMeter is running, it shows a small green box at the right-hand end of the section just under the menu bar.

You can also check the “Run” menu. If “Start” is disabled, and “Stop” is enabled, then JMeter is running your test plan (or, at least, it thinks it is).

The numbers to the left of the green box are the number of active threads / total number of threads. These only apply to a locally run test; they do not include any threads started on remote systems when using client-server mode.

Stopping a Test

There are two types of stop command available from the menu:

  • Stop (Control + ‘.’) – stops the threads immediately if possible. In Versions of JMeter after 2.3.2, many samplers are now Interruptible which means that active samples can be terminated early. The stop command will check that all threads have stopped within the default timeout, which is 5000 ms = 5 seconds. [This can be changed using the JMeter propertyjmeterengine.threadstop.wait ] If the threads have not stopped, then a message is displayed. The Stop command can be retried, but if it fails, then it is necessary to exit JMeter to clean up.
  • Shutdown (Control + ‘,’)- requests the threads to stop at the end of any current work. Will not interrupt any active samples. The modal shutdown dialog box will remain active until all threads have stopped.

Versions of JMeter after 2.3.2 allow a Stop to be initiated if Shutdown is taking too long. Close the Shutdown dialog box and select Run/Stop, or just press Control + ‘.’.

When running JMeter in non-GUI mode, there is no Menu, and JMeter does not react to keystrokes such as Control + ‘.’. So in versions after 2.3.2, JMeter non-GUI mode will listen for commands on a specific port (default 4445, see the JMeter property jmeterengine.nongui.port ). In versions after 2.4, JMeter supports automatic choice of an alternate port if the default port is being used (for example by another JMeter instance). In this case, JMeter will try the next higher port, continuing until it reaches the JMeter property jmeterengine.nongui.maxport) which defaults to 4455. If maxport is less than or equal to port , port scanning will not take place. Note that JMeter 2.4 and earlier did not set up the listener for non-GUI clients, only non-GUI standalone tests; this has been fixed.

The chosen port is displayed in the console window.

The commands currently supported are:

  • Shutdown – graceful shutdown
  • StopTestNow – immediate shutdown

These commands can be sent by using the shutdown[.cmd|.sh] orstoptest[.cmd|.sh] script respectively. The scripts are to be found in the JMeter bin directory. The commands will only be accepted if the script is run from the same host.

Become Vskills Certified JMeter Tester. Learn the module “Building A Test Plan”. Try the free practice test!

Test Your Software Testing Skills By Taking Our JMeter Practice Tests On This Link

Apply For JMeter Certification

Go back to Tutorial

Share this post
[social_warfare]
Installing and Running JMeter
Controllers

Get industry recognized certification – Contact us

keyboard_arrow_up