Agile Project Management Sample Questions


Sample Questions
 

 

1. Which of the following does not forms a part of the sprint
A. Show and Tell
B. Retrospective
C. Chicken & Pig meeting
D. None of the above

2. What is the name given to the to-do list for the sprint, prepared by the scrum master
A. Release Backlog    
B. Scrum Report
C. Product Backlog
D. Sprint Backlog

3. Which of the following term refers to the 15 minutes team meeting, held daily
A. Backlog Meeting
B. Daily Scrum
C. Review Meeting
D. None of the above

4. Who is responsible for removing impediment
A. Product Owner
B. Scrum Master
C. Manager
D. None of the above

5. Which of the following shows remaining work in a release.
A. Release Burndown Chart
B. Sprint Burndown Chart
C. Product Review Chart
D. None of the above


Answers:      1 (C), 2 (D), 3 (B), 4 (B), 5 (A)



Apply for certification

https://www.vskills.in/certification/project-management/certificate-in-agile-project-management



 For Support